25 May 2010
Denca’s brief consisted of upgrading the existing system by adding controls, modifying software, configuring and integrating new hardware into the existing Duerr’s process, installing all necessary cables and putting the new system into service.Process diagrams were drawn up and interpreted as a control philosophy programme employing a Siemens S7 300 PLC controller and a Siemens MP 270 HMI screen and new components built into the existing panels. When the system was up and running, a testing procedure was implemented.